American Electric Power — Jul 30, 2026 release

Fiscal 2026 second-quarter results · 8-K Item 2.02 · Exhibit 99.1 · 0000004904-26-000055
Open on SEC.gov ↗
Showing in the filing
Expected savings in interest costs from DOE loan
“$685 million”
Period
No period stated
Measure
Company-defined measure
Source
Prose
All guidance in this release · 15
Operating earnings for FY2026
“$6.25 to $6.55 per share”
Expected cost offsets from load growth
“up to $16 billion”
Expected customer savings from federal loan …
“$1.4 billion”
New load additions (contracted load growth) for FY2030
“69 gigawatts (GW)”
Annual operating earnings growth rate for the long term
“7% to 9%”
Operating earnings CAGR for the long term
“greater than 9%”
Operating earnings compound annual growth ra… for the long term
“greater than 9%”
Capital investment plan for the long term
“$78 billion”
Five-year capital plan for the long term
“$78 billion”
Incremental capital investments (line of sig…
“more than $10 billion”
Expected savings in interest costs from DOE …
“$685 million”
Projected customer savings through lower int…
“nearly $1 billion”
Additional turbine capacity under evaluation for FY2035
“up to 10 GW”
Estimated GAAP EPS for FY2026
“$6.16 to $6.46”
Estimated earnings per share on a GAAP basis
“$6.16 to $6.46 per share”
Exhibit 99.1 · the passage around this item
… earlier in the release
As an additional affordability measure, AEP continues to utilize grants and low-cost loans from the U.S. Department of Energy (DOE) to drive customer savings. Most recently, AEP Texas secured a DOE loan for up to $3.3 billion to support nearly 100 transmission projects, which is expected to save customers $685 million in interest costs over the life of the loan. 1 With this financing, AEP has now secured approximately $5 billion in DOE loans across its portfolio, supporting nearly $1 billion in projected customer savings through lower interest costs. Combined with almost $400 million in awarded DOE grants, this DOE funding is expected to deliver nearly $1.4 billion in estimated customer benefits over the life of the loans and grants. AEP’s operating companies continued to deliver productive regulatory outcomes during the second quarter. These included approval of a distribution base rate decrease for customers in Ohio, approval to add 1.3 GW of generation resources for Oklahoma customers, and completion of a $1.4 billion securitization that allowed Appalachian Power to file its lowest increase in a base rate request in Virginia in nearly 30 years. Virginia also approved a large load tariff in the second quarter, bringing the total number of AEP’s states with approved large load tariffs to five, with three additional state filings pending approval. "As electricity demand accelerates, we have seen firsthand how growth can lower costs and improve affordability for existing customers. That is why w
later in the release …
the item shown at left
other guidance in this release
Text is the filed exhibit, verbatim.