Palmarejo adjusted CAS per gold ounce
“$700 - $900 per gold ounce”
Period
FY2026
Measure
Company-defined measure
Source
Prose
All guidance in this release · 102
Production for FY2026
“approximately 690,000 ounces of gold, 20 million ounces of silver, and 45 million pounds of copper”
Copper production for FY2026
“45 million pounds”
Adjusted EBITDA for FY2026
“$2.3 billion”
Free cash flow for FY2026
“$1.5 billion”
Year-end cash balance for FY2026
“approaching $2.0 billion”
Mining rate (New Afton C-Zone) for Q4 FY2026
“increase to 16,000 tonnes per day”
New Afton prorated gold production for FY2026
“50,000 - 60,000 ounces”
New Afton copper production for FY2026
“40 - 50”
New Afton prorated copper production for FY2026
“40 - 50 million pounds”
Total copper production for FY2026
“40 - 50”
New Afton prorated silver production for FY2026
“100,000 - 180,000 ounces”
New Afton prorated adjusted CAS per gold ounce for FY2026
“$1,300 - $1,600 per gold ounce”
New Afton prorated adjusted CAS per pound of… for FY2026
“$2.00 - $2.30 per pound of copper”
New Afton prorated capital expenditures for FY2026
“$51 - $61 million”
Prorated capital expenditures (New Afton)
“$51 - $61 million”
New Afton prorated exploration investment for FY2026
“$19 - $23 million”
Prorated exploration investment (New Afton)
“$19 - $23 million ($17 - $19 million expensed and $2 - $4 million capitalized)”
Underground production rate (Rainy River)
“ramp up to 5,000 tonnes per day”
Rainy River prorated gold production for FY2026
“190,000 - 230,000 ounces”
Rainy River prorated silver production for FY2026
“380,000 - 450,000 ounces”
Rainy River (by-product) Gold ($/oz) for FY2026
“$2,700 - $3,000”
Rainy River prorated adjusted CAS per gold o… for FY2026
“$2,700 - $3,000 per gold ounce”
Prorated adjusted CAS (Rainy River)
“$2,700 - $3,000 per gold ounce”
Rainy River prorated capital expenditures for FY2026
“$150 - $170 million”
Prorated capital expenditures (Rainy River)
“$150 - $170 million”
Rainy River prorated exploration investment for FY2026
“$8 - $10 million”
Prorated exploration investment (Rainy River)
“$8 - $10 million (substantially all expensed)”
Las Chispas full-year gold production for FY2026
“55,000 - 65,000 ounces”
Production (Las Chispas) for FY2026
“55,000 - 65,000 ounces of gold and 5.5 - 6.3 million ounces of silver”
Las Chispas full-year silver production for FY2026
“5.5 - 6.3 million ounces”
Adjusted CAS (Las Chispas) for FY2026
“$750 - $950 per gold ounce and $12.50 - $14.50 per silver ounce”
Las Chispas adjusted CAS per gold ounce for FY2026
“$750 - $950 per gold ounce”
Las Chispas adjusted CAS per silver ounce for FY2026
“$12.50 - $14.50 per silver ounce”
Capital expenditures (Las Chispas) for FY2026
“$71 - $84 million”
Exploration investment (Las Chispas) for FY2026
“$21 - $26 million ($11 - $14 million expensed and $10 - $12 million capitalized)”
Las Chispas exploration investment for FY2026
“$21 - $26 million”
Palmarejo 2026 gold sales sold under gold st… for FY2026
“approximately 40% - 50%”
Palmarejo full-year gold production for FY2026
“95,000 - 105,000 ounces”
Production (Palmarejo) for FY2026
“95,000 - 105,000 ounces of gold and 6.25 - 7.0 million ounces of silver”
Palmarejo full-year silver production for FY2026
“6.25 - 7.0 million ounces”
Adjusted CAS (Palmarejo) for FY2026
“$700 - $900 per gold ounce and $21.50 - $23.50 per silver ounce”
Palmarejo adjusted CAS per gold ounce for FY2026
“$700 - $900 per gold ounce”
Palmarejo (co-product) Silver ($/oz) for FY2026
“$21.50 - $23.50”
Palmarejo adjusted CAS per silver ounce for FY2026
“$21.50 - $23.50 per silver ounce”
Capital expenditures (Palmarejo) for FY2026
“$35 - $41 million”
Exploration investment (Palmarejo) for FY2026
“$24 - $28 million ($22 - $24 million expensed and $2 - $4 million capitalized)”
Palmarejo exploration investment for FY2026
“$24 - $28 million”
Production (Rochester) for FY2026
“6.4 - 7.8 million ounces of silver and 70,000 - 90,000 ounces of gold”
Rochester full-year silver production for FY2026
“6.4 - 7.8 million ounces”
Rochester full-year gold production for FY2026
“70,000 - 90,000 ounces”
Adjusted CAS (Rochester) for FY2026
“$23.00 - $25.00 per silver ounce and $1,350 - $1,550 per gold ounce”
Rochester (co-product) Silver ($/oz) for FY2026
“$23.00 - $25.00”
Rochester adjusted CAS per silver ounce for FY2026
“$23.00 - $25.00 per silver ounce”
Rochester adjusted CAS per gold ounce for FY2026
“$1,350 - $1,550 per gold ounce”
Capital expenditures (Rochester) for FY2026
“$96 - $110 million”
Exploration investment (Rochester) for FY2026
“$14 - $17 million ($7 - $9 million expensed and $7 - $8 million capitalized)”
Rochester exploration investment for FY2026
“$14 - $17 million”
Kensington full-year gold production for FY2026
“98,000 - 110,000 gold ounces”
Kensington adjusted CAS per gold ounce for FY2026
“$1,750 - $1,950 per gold ounce”
Capital expenditures (Kensington) for FY2026
“$54 - $63 million”
Exploration investment (Kensington) for FY2026
“$14 - $15 million ($8 - $9 million expensed and $6 - $6 million capitalized)”
Kensington exploration investment for FY2026
“$14 - $15 million”
Production (Wharf) for FY2026
“72,000 - 90,000 ounces of gold and 50,000 - 200,000 ounces of silver”
Wharf full-year gold production for FY2026
“72,000 - 90,000 ounces”
Wharf full-year silver production for FY2026
“50,000 - 200,000 ounces”
Wharf adjusted CAS per gold ounce for FY2026
“$1,400 - $1,600 per gold ounce”
Capital expenditures (Wharf) for FY2026
“$17 - $23 million”
Exploration investment (Wharf) for FY2026
“$10 - $12 million ($8 - $9 million expensed and $2 - $3 million capitalized)”
Wharf exploration investment for FY2026
“$10 - $12 million”
Total 2026 exploration investment - expansio… for FY2026
“$118 - $132 million”
Total exploration investment for FY2026
“$118 - $132 million for expansion drilling (classified as exploration expense) and $29 - $37 million for infill drilling (capitalized exploration) for a total expected investment of $147 - $169 million”
Total 2026 exploration investment - infill d… for FY2026
“$29 - $37 million”
Total 2026 exploration investment for FY2026
“$147 - $169 million”
Capital expenditure for FY2026
“$520 - $605 million”
Cash income and mining tax for FY2026
“$350 - $450 million”
Amortization for FY2026
“$1.1 - $1.2 billion”
New Afton silver production for FY2026
“100 - 180”
Rainy River silver production for FY2026
“380 - 450”
Las Chispas silver production for FY2026
“5,500 - 6,300”
Palmarejo Silver (K oz) for FY2026
“6,250 - 7,000”
Palmarejo silver production for FY2026
“6,250 - 7,000”
Rochester Silver (K oz) for FY2026
“6,400 - 7,800”
Rochester silver production for FY2026
“6,400 - 7,800”
Wharf Silver (K oz) for FY2026
“50 - 200”
Wharf silver production for FY2026
“50 - 200”
Total gold production for FY2026
“630,000 - 750,000”
Total Silver (K oz) for FY2026
“18,680 - 21,930”
Total silver production for FY2026
“18,680 - 21,930”
Las Chispas (co-product) Gold ($/oz) for FY2026
“$750 - $950”
Palmarejo (co-product) Gold ($/oz) for FY2026
“$700 - $900”
Rochester (co-product) Gold ($/oz) for FY2026
“$1,350 - $1,550”
Kensington Gold ($/oz) for FY2026
“$1,750 - $1,950”
Wharf (by-product) Gold ($/oz) for FY2026
“$1,400 - $1,600”
Capital Expenditures, Sustaining for FY2026
“$360 - $405”
Capital Expenditures, Development for FY2026
“$160 - $200”
Exploration, Expensed for FY2026
“$118 - $132”
Exploration, Capitalized for FY2026
“$29 - $37”
General & Administrative Expenses for FY2026
“$90 - $100”
Effective Tax Rate (%) for FY2026
“34% - 38%”
New Afton (co-product) Gold ($/oz) for FY2026
“$1,300 - $1,600”
Las Chispas (co-product) Silver ($/oz) for FY2026
“$12.50 - $14.50”
New Afton (co-product) Copper ($/lb) for FY2026
“$2.00 - $2.30”
Exhibit 99.1 · the passage around this item
… earlier in the release
The Company anticipates approximately 40% - 50% of Palmarejo’s 2026 gold sales will be sold under the gold stream agreement Guidance • Full-year 2026 production is expected to be 95,000 - 105,000 ounces of gold and 6.25 - 7.0 million ounces of silver, which is unchanged from the previous guidance ranges • Adjusted CAS 1 in 2026 are expected to be $700 - $900 per gold ounce and $21.50 - $23.50 per silver ounce, which are unchanged from the previous guidance ranges • Capital expenditures in 2026 are expected to be $35 - $41 million, consisting primarily of sustaining capital and underground development, which are unchanged from the previous guidance ranges • Exploration investment in 2026 is expected to be $24 - $28 million ($22 - $24 million expensed and $2 - $4 million capitalized), which is unchanged from the previous guidance ranges Rochester, United States (Dollars in millions, except per ounce amounts) 2Q 2026 1Q 2026 4Q 2025 3Q 2025 2Q 2025 Ore tonnes placed 8,041,787  6,724,626  9,275,732  7,535,326  7,122,912  Average silver grade (grams/tonne) 10  12  17  19  20  Average gold grade (grams/tonne) 0.07  0.07  0.08  0.08  0.09  Silver ounces produced (000’s) 1,225  1,394  1,748  1,644  1,456  Gold ounces produced 11,671  14,112  17,722  14,801  14,302  Silver ounces sold (000’s) 1,235  1,387  1,701  1,656  1,438  Gold ounces sold 11,748  14,090  18,043  13,975  13,881  Average realized price per silver ounce $ 71.53  $ 81.59  $ 54.85  $ 38.95  $ 33.88  Average realized price per gold ounce $ 4,461  $ 4,843  $ 4,139  $ 3,431  $ 3,333  Metal sale