Oil production - MBO/d (total - MBOE/d)
“470 - 475 (860 - 875)”
Period
Q1 FY2025
Measure
Company-defined measure
Source
Guidance table
All guidance in this release · 44
Annual base dividend for FY2024
“$4.00 per share”
Base cash dividend for Q4 FY2024
“$1.00 per share”
Oil production for FY2025
“485 - 498 MBO/d (883 - 909 MBOE/d)”
Cash capital expenditures for FY2025
“$3.8 - $4.2 billion”
Gross (net) wells expected to be drilled for FY2025
“446 - 471 gross (406 - 428 net) wells”
Wells completed for FY2025
“between 557 - 592 gross (526 - 560 net)”
Gross (net) wells expected to be completed for FY2025
“557 - 592 gross (526 - 560 net) wells”
Oil production for Q1 FY2025
“470 - 475 MBO/d ( 860 - 875 MBOE/d)”
Cash capital expenditures for Q1 FY2025
“$900 million - $1.0 billion”
Implied run-rate oil production for Q2 FY2025
“490 – 505 MBO/d (891 – 920 MBOE/d)”
Implied full year 2025 oil production per mi… for FY2025
“44.8, 10% better than the Company’s original pro forma 2025 outlook provided in February 2024”
Remaining share buyback authorization
“approximately $2.5 billion”
Net production - MBOE/d for FY2025
“883 - 909”
Oil production - MBO/d for FY2025
“485 - 498”
Oil production - MBO/d (total - MBOE/d) for Q1 FY2025
“470 - 475 (860 - 875)”
Oil production - MBO/d (total - MBOE/d), Dia… for Q1 FY2025
“470 - 475 (860 - 875)”
Oil production - MBO/d (total - MBOE/d), Vip… for Q1 FY2025
“30.0 - 31.0 (54.0 - 56.0)”
Lease operating expenses, including workover… for FY2025
“$5.90 - $6.30”
Lease operating expenses, including workovers
“$5.90 - $6.30”
Cash G&A ($/BOE) for FY2025
“$0.60 - $0.75”
Cash G&A
“$0.60 - $0.75”
Non-cash equity-based compensation ($/BOE) for FY2025
“$0.25 - $0.35”
Non-cash equity-based compensation
“$0.25 - $0.35”
DD&A ($/BOE) for FY2025
“$14.00 - $15.00”
Interest expense (net of interest income) ($… for FY2025
“$0.25 - $0.50”
Interest expense (net of interest income)
“$0.25 - $0.50”
Gathering, processing and transportation ($/… for FY2025
“$1.20 - $1.40”
Gathering, processing and transportation
“$1.20 - $1.40”
Production and ad valorem taxes (% of revenue) for FY2025
“~7%”
Corporate tax rate (% of pre-tax income) for FY2025
“23%”
Cash tax rate (% of pre-tax income) for FY2025
“17% - 20%”
Cash taxes ($ - million) for Q1 FY2025
“$280 - $340”
Operated drilling and completion ($ - million) for FY2025
“$3,130 - $3,440”
Capital workovers, non-operated properties a… for FY2025
“$280 - $320”
Infrastructure, environmental and midstream … for FY2025
“$390 - $440”
Total capital expenditures for FY2025
“$3,800 - $4,200”
Capital expenditures for Q1 FY2025
“$900 - $1,000”
Horizontal wells completed (net)
“557 - 592 (526 - 560)”
Average lateral length (Ft.) for FY2025
“~11,500'”
Midland Basin well costs per lateral foot for FY2025
“$555 - $605”
Midland Basin well costs per lateral foot for FY2025
“$555 - $605”
Delaware Basin well costs per lateral foot for FY2025
“$860 - $910”
Midland Basin completed net lateral feet (%) for FY2025
“~95%”
Delaware Basin completed net lateral feet (%) for FY2025
“~5%”
Exhibit 99.1 · the passage around this item
… earlier in the release
This guidance gives effect to the estimated contribution related to the pending Double Eagle acquisition, which is expected to close on April 1, 2025, subject to the satisfaction of customary closing conditions and regulatory approval. 2025 Guidance 2025 Guidance Diamondback Energy, Inc. Viper Energy, Inc. 2025 Net production - MBOE/d 883 - 909 2025 Oil production - MBO/d 485 - 498 Q1 2025 Oil production - MBO/d (total - MBOE/d) 470 - 475 (860 - 875) 30.0 - 31.0 (54.0 - 56.0) Unit costs ($/BOE) Lease operating expenses, including workovers $5.90 - $6.30 G&A Cash G&A $0.60 - $0.75 Non-cash equity-based compensation $0.25 - $0.35 DD&A $14.00 - $15.00 Interest expense (net of interest income) $0.25 - $0.50 Gathering, processing and transportation $1.20 - $1.40 Production and ad valorem taxes (% of revenue) ~7% Corporate tax rate (% of pre-tax income) 23% Cash tax rate (% of pre-tax income) 17% - 20% Q1 2025 Cash taxes ($ - million) $280 - $340 Capital Budget ($ - million) Operated drilling and completion $3,130 - $3,440 Capital workovers, non-operated properties and science $280 - $320 Infrastructure, environmental and midstream (1) $390 - $440 2025 Total capital expenditures $3,800 - $4,200 Q1 2025 Capital expenditures $900 - $1,000 Gross horizontal wells drilled (net) 446 - 471 (406 - 428) Gross horizontal wells completed (net) 557 - 592 (526 - 560) Average lateral length (Ft.) ~11,500' FY 2025 Midland Basin well costs per lateral foot $555 - $605 FY 2025 Delaware Basin well costs per lateral foot $860 - $910 Midland Basin completed net lateral feet (%) ~95% Delaware Basin completed net lateral feet (%) ~5% (1) Includes approxi
later in the release …
the item shown at left
other guidance in this release
Text is the filed exhibit, verbatim.