Hecla Mining — Feb 13, 2025 release
Fiscal 2024 fourth-quarter results · 8-K Item 2.02 · Exhibit 99.1 · 0001437749-25-003775
Showing in the filing
Keno Hill expected increase in throughput
“600 tons per day”
Period
No period stated
Measure
Company-defined measure
Source
Prose
All guidance in this release · 58
Casa Berardi 160 pit gold production
“until 2027”
Casa Berardi production gap
“commencing in 2027 and continuing until 2032 or later”
Quarterly common stock dividend declared for FY2025
“$0.00375 per share”
Quarterly Series B preferred stock dividend … for FY2025
“$0.875 per share”
Consolidated silver production for FY2025
“15.5-17.0 million ounces”
Total consolidated silver production (Moz) for FY2025
“15.5 - 17.0”
Greens Creek silver production for FY2025
“8.1-8.8 million ounces”
Lucky Friday silver production for FY2025
“4.7-5.1 million ounces”
Keno Hill silver production for FY2025
“2.7-3.1 million ounces”
Consolidated gold production for FY2025
“120-130 thousand ounces”
Greens Creek Silver Production (Moz) for FY2025
“8.1 - 8.8”
Greens Creek Gold Production (Koz) for FY2025
“44.0 - 48.0”
Greens Creek silver-equivalent production (M… for FY2025
“18.0 - 19.5”
Greens Creek gold-equivalent production (Koz) for FY2025
“200.0 - 210.0”
Lucky Friday Silver Production (Moz) for FY2025
“4.7 - 5.1”
Lucky Friday Gold Production (Koz) for FY2025
“N/A”
Lucky Friday silver-equivalent production (M… for FY2025
“8.0 - 8.5”
Lucky Friday gold-equivalent production (Koz) for FY2025
“90.0 - 95.0”
Casa Berardi Silver Production (Moz) for FY2025
“N/A”
Casa Berardi gold-equivalent production (Koz) for FY2025
“76.0 - 82.0”
Casa Berardi silver-equivalent production (M… for FY2025
“6.5 - 7.5”
Keno Hill Silver Production (Moz) for FY2025
“2.7 - 3.1”
Keno Hill Gold Production (Koz) for FY2025
“N/A”
Keno Hill silver-equivalent production (Moz) for FY2025
“3.0 - 3.5”
Keno Hill gold-equivalent production (Koz) for FY2025
“30.0 - 40.0”
Total consolidated gold production (Koz) for FY2025
“120.0 - 130.0”
Total consolidated silver-equivalent product… for FY2025
“35.5 - 39.0”
Total consolidated gold-equivalent productio… for FY2025
“396.0 - 427.0”
Keno Hill production costs, excluding deprec… for FY2025
“$15-$17 million per quarter”
Keno Hill production costs, excluding deprec…
“$15-$17 million”
Greens Creek Total Costs of Sales (million) for FY2025
“289.0”
Greens Creek Cash costs, after by-product cr… for FY2025
“$2.00 - $2.50”
Greens Creek AISC, after by-product credits,… for FY2025
“$8.75 - $9.50”
Lucky Friday Total Costs of Sales (million) for FY2025
“135.0”
Lucky Friday Cash costs, after by-product cr… for FY2025
“$4.25 - $4.75”
Lucky Friday AISC, after by-product credits,… for FY2025
“$16.50 - $18.00”
Total Silver Total Costs of Sales (million) for FY2025
“424.0”
Total Silver cash costs per silver ounce, af… for FY2025
“$3.00 - $3.25”
Total Silver AISC per silver ounce, after by… for FY2025
“$15.75 - $17.00”
Casa Berardi Total Costs of Sales (million) for FY2025
“165.5”
Casa Berardi Cash costs, after by-product cr… for FY2025
“$1,500 - $1,650”
Casa Berardi AISC, after by-product credits,… for FY2025
“$1,750 - $1,950”
Consolidated capital investment for FY2025
“$222-$242 million”
Lucky Friday reserve mine-life for the long term
“seventeen years”
Total Capital expenditures - Total (millions) for FY2025
“$222 - $242”
Total Capital expenditures - Sustaining (mil… for FY2025
“$125 - $133”
Total Capital expenditures - Growth (millions) for FY2025
“$97 - $109”
Greens Creek Capital expenditures - Total (m… for FY2025
“$58 - $63”
Greens Creek Capital expenditures - Sustaini… for FY2025
“$48 - $51”
Greens Creek Capital expenditures - Growth (… for FY2025
“$10 - $12”
Lucky Friday Capital expenditures - Total (m… for FY2025
“$63 - $68”
Lucky Friday Capital expenditures - Sustaini… for FY2025
“$58 - $61”
Lucky Friday Capital expenditures - Growth (… for FY2025
“$5 - $7”
Casa Berardi Capital expenditures - Sustaini… for FY2025
“$19 - $21”
Casa Berardi Capital expenditures - Growth (… for FY2025
“$39 - $42”
Keno Hill Capital expenditures - Growth (mil… for FY2025
“$43 - $48”
Exploration & Pre-Development expenditures -… for FY2025
“$28”
Keno Hill expected increase in throughput
“600 tons per day”
Exhibit 99.1 · the passage around this item
… earlier in the release
Such forward-looking statements may include, without limitation: (i) Silver grades at Greens Creek are expected to increase through the first quarter of 2025 as backfill cycles improve; (ii) production is expected to increase at Keno Hill in 2026; (iii) Yukon Energy Corporation's out-of-service hydro-electric turbine is expected to be repaired by summer 2025; (iv) Keno Hill's expected increase in throughput to 600 tons per day and production growth to sustainable profitable production is expected to meet the Company's investment threshold criteria at current silver prices; (v) Casa Berardi is expected to 1) continue underground production through mid-2025, 2) produce gold from the 160 pit until 2027, and 3) have a production gap commencing in 2027 to 2032 or later. During this time, the focus is expected to be on investing in infrastructure and equipment, permitting and de-watering and stripping two expected new open pits, Principal and West Mine Crown Pillar. Upon conclusion of the hiatus and related permitting and construction, the Company expects the mine to generate significant free cash flow, particularly at current gold prices; (vi) projected total cost of sales, as well as cash costs and AISC per ounce (in each case after by-product credits) for Greens Creek, Lucky Friday, and Casa Berardi individually and for silver overall for 2025; (vii) Lucky Friday's reserve mine-life is expected to be eighteen years; (viii) Company-wide and mine-specific estimated spending on capital, exploration and predevelopment for 2025; and (ix) Company-wide and mine-specific estimated silver, gold, silver-equivalent a
later in the release …
the item shown at left
other guidance in this release
Text is the filed exhibit, verbatim.