FPL full-year capital investments
“between $9.3 billion and $9.8 billion”
Period
FY2025
Measure
Company-defined measure
Source
Prose
All guidance in this release · 8
Capital investments for FY2025
“between $9.3 billion and $9.8 billion”
FPL full-year capital investments for FY2025
“between $9.3 billion and $9.8 billion”
Typical residential customer bill increase (… for FY2025
“about 2% on average”
Duane Arnold nuclear plant contribution to a… for FY2025
“up to $0.16”
Adjusted earnings per share for FY2025
“$3.45 to $3.70”
Adjusted earnings per share for FY2026
“$3.63 to $4.00”
Adjusted earnings per share for FY2027
“$3.85 to $4.32”
Dividends per share growth rate for FY2026
“roughly 10% rate per year”
Exhibit 99.1 · the passage around this item
… earlier in the release
FPL's growth in the third quarter of 2025 primarily was driven by continued investment in the business. FPL's capital expenditures were approximately $2.5 billion for the quarter, and full-year capital investments are expected to be between $9.3 billion and $9.8 billion. Regulatory capital employed increased by approximately 8% over the same quarter last year. By making smart capital investments for the benefit of customers and being best-in-class on costs, FPL continues to deliver its strong customer value proposition of high reliability, outstanding customer service and low bills. In one of the nation's fastest-growing states and the world's 16th largest economy, FPL is both creating value for its customers and diversifying its generation fleet by adding cost-effective solar and storage to the nation's largest gas-fired fleet and its four nuclear units that make up the backbone of its generation fleet. 1 On Feb. 28, FPL initiated its 2025 base rate proceeding for new rates, effective in January 2026. FPL reached a proposed settlement agreement in August with most of the intervenors in the proceeding, reflecting a broad set of constituents across its customer base. FPL believes the proposed settlement is fair, balanced and constructive, and supports its continued ability to provide highly reliable, low-cost service for its customers through the end of the decade. If the proposed agreement is approved, a typical residential customer bill would on
later in the release …