Southern Copper — Oct 28, 2025 release
Fiscal 2025 third-quarter results · 8-K Item 2.02 · Exhibit 99.1 · 0001104659-25-103333
Showing in the filing
Tia Maria jobs upon operations start
“764 direct jobs and 5,900 indirect jobs”
Period
FY2027
Measure
Company-defined measure
Source
Prose
All guidance in this release · 19
Quarterly cash dividend for FY2025
“$0.90 per share of common stock”
Stock dividend for FY2025
“0.0085 shares of common stock per share of common stock”
Long-term copper production goal for the long term
“1.6 million tonnes of copper”
Capital investment program (current decade)
“exceeds $15 billion”
Peruvian projects capital investment
“could surpass $10.3 billion”
Tia Maria annual production capacity for FY2025
“120,000 tonnes of SX- EW copper cathodes per year”
Tia Maria expected export revenue
“$18.2 billion”
Tia Maria expected taxes and royalties
“$3.8 billion”
Tia Maria project budget
“$1,802 million”
Tia Maria jobs upon operations start for FY2027
“764 direct jobs and 5,900 indirect jobs”
Los Chancas annual production for FY2025
“130,000 tonnes of copper and 7,500 tonnes of molybdenum annually”
Los Chancas estimated capital investment
“$2.6 billion”
Los Chancas operations start
“2030-2031”
Michiquillay annual production for FY2025
“225,000 tonnes of copper per year”
Michiquillay initial mine life
“more than 25 years”
Michiquillay estimated investment
“approximately $2.5 billion”
Michiquillay production start-up
“2032”
Mexican projects investment
“$10.2 billion”
El Arco project design capacity
“120 ktpd concentrator and 28 ktpy SX-EW operations”
Exhibit 99.1 · the passage around this item
… earlier in the release
To the fullest extent possible, we intend to fill the 3,500 jobs estimated to be required during Tia Maria ´ s construction phase with workers from the Islay province. In 2027, when we start operations, the project will generate 764 direct jobs and 5,900 indirect jobs. In the early construction phase, progress on access roads and platforms stands at 90%. We will advance these efforts alongside work to set up a temporary camp; engage in massive earthworks; and roll out mine-opening activities. As of October 14, 2025, the Company received from the Ministry of Energy and Mines an authorization for the commencement of exploitation activities for the Tía María project. This authorization is based on the considerations 3Q25 www.southerncoppercorp.com Page 3 of 12 THIRD QUARTER AND NINE MONTHS 2025 RESULTS SOUTHERN COPPER outlined in the supporting technical report and the environmental certification approved for the project. Consequently, we will soon initiate pre-stripping activities in La Tapada, and begin building main project components. Los Chancas - Apurimac: This greenfield project, located in Apurimac, Peru, is a copper and molybdenum porphyry deposit. Current estimates of indicated copper mineral resources are 98 million tonnes of oxides with a copper content of 0.45% and 52 million tonnes of sulfides with a copper content of 0.59%. The Los Chancas project envisions an open-pit mine with a combined operati
later in the release …
the item shown at left
other guidance in this release