Current capital investment program (this decade)
“exceeds $15 billion”
Period
No period stated
Measure
Company-defined measure
Source
Prose
All guidance in this release · 15
Quarterly cash dividend declared for FY2025
“$0.70 per share of common stock”
Stock dividend declared for FY2025
“0.0099 shares of common stock per share of common stock”
Current capital investment program (this dec…
“exceeds $15 billion”
Minera Mexico planned capital investment for FY2025
“more than $600 million”
El Arco planned concentrator and SX-EW capac…
“120 ktpd concentrator and 28 ktpy SX-EW operations”
Tia Maria production capacity
“120,000 tons of SX- EW copper cathodes per year”
Tia Maria expected exports
“$18.2 billion”
Tia Maria expected contribution in taxes and…
“$3.8 billion in taxes and royalties”
Tia Maria project budget
“$1,802 million”
Los Chancas planned annual production for FY2025
“130,000 tons of copper and 7,500 tons of molybdenum annually”
Los Chancas estimated capital investment
“$2.6 billion”
Los Chancas operations start for FY2031
“operations are expected to begin in 2031”
Michiquillay expected annual copper production for FY2025
“225,000 tons of copper per year”
Michiquillay estimated investment required
“approximately $2.5 billion”
Michiquillay production start-up for FY2032
“expect production start-up by 2032”
Exhibit 99.1 · the passage around this item
… earlier in the release
” ​ ​ ​ 1Q25 www.southerncoppercorp.com Page 2 of 12 ​ ​ ​ ​ ​ ​ ​ ​ ​ FIRST QUARTER 2025 RESULTS SOUTHERN COPPER ​ ​ ​ ​ Key Financial Data ​ ​ ​ 1Q25 ​ 1Q24 ​ Variance ​ 4Q24 ​ Variance ​ ​ ​ ​ ​ ​ $ % ​ ​ ​ $ % ​ ​ ​ (in million except per share amount and %s) Sales      $ 3,121.9      $ 2,599.8      $ 522.1 ​ 20.1% ​ $ 2,784.3      $ 337.6 ​ 12.1% Cost of sales ​   1,319.2 ​   1,157.6 ​   161.6 ​ 14.0% ​   1,211.9 ​   107.3 ​ 8.9% Operating income ​   1,535.5 ​   1,189.7 ​   345.8 ​ 29.1% ​   1,307.3 ​   228.2 ​ 17.5% Net income ​ $ 945.9 ​ $ 736.0 ​ $ 209.9 ​ 28.5% ​ $ 793.9 ​ $ 152.0 ​ 19.1% Net income margin ​   30.3% ​   28.3% ​   2pps ​ 7.1% ​   28.5% ​   1.8pps ​ 6.3% Adjusted EBITDA ​   1,745.6 ​   1,417.7 ​   327.9 ​ 23.1% ​   1,506.7 ​   238.9 ​ 15.9% Adjusted EBITDA margin ​   55.9% ​   54.5% ​   1.4pps ​ 2.6% ​   54.1% ​   1.8pps ​ 3.3% Income per share ​ $ 1.19 ​ $ 0.95 ​ $ 0.24 ​ 25.3% ​ $ 1.01 ​ $ 0.18 ​ 17.8% Capital investments ​   317.8 ​   213.8 ​   104.0 ​ 48.6% ​   235.3 ​   82.5 ​ 35.1% ​ Capital Investments ​ Our current capital investment program for this decade exceeds $15 billion and includes investments in projects in Mexico and Peru. ​ Mexican Projects ​ Minera Mexico is planning to invest more than $600 million in 2025 at both its open pit and underground mines. Half of this investment will be used to guarantee the viability of long-term operations by actively modernizing and updating assets. The remaining funds will target improvements in water usage and tailings management to ensure safety and efficiency in our operations. In addition, we will invest in efforts to bolster optimization and growth. ​ El Arco - Baja California: This is a world-class copper deposit located in the central part of the Baja California peninsula with sulfide ore reserves of over 1,230 million tonnes and an average ore grade of 0.40%, and 141 million tonnes of leach material with an average ore grade of 0.27%. The project includes an open-pit mine with a combined 120 ktpd concentrator and 28 ktpy SX-EW operations. ​ Detailed engineering is still underway for the concentrator, SX-EW plant, water desalination, logistics infrastructure and power delivery. ​ SCC has several projects in its Mexican pipeline that may boost organic growth if they are found to be of value for both sta
later in the release …
the item shown at left
other guidance in this release
Text is the filed exhibit, verbatim.