Lucky Friday silver production
“4.7-5.1 million ounces of silver”
Period
FY2025
Measure
Company-defined measure
Source
Prose
All guidance in this release · 65
Annual interest expense savings from Notes r… for FY2025
“$17.8 million annually”
Keno Hill Capital expenditures - Sustaining … for FY2025
“$0”
Greens Creek silver production for FY2025
“8.1-8.8 million ounces of silver”
Greens Creek gold production for FY2025
“50.0-55.0 thousand ounces”
Greens Creek Silver Equivalent (Moz) for FY2025
“18.0 - 19.5”
Greens Creek silver equivalent ounce for FY2025
“18.0-19.5 million silver equivalent ounces”
Greens Creek total cost of sales for FY2025
“$289 million”
Greens Creek AISC, after by-product credits,… for FY2025
“$0.00-$1.50”
Greens Creek Capital expenditures - Sustaini… for FY2025
“$48 - $51”
Greens Creek capital investment for FY2025
“$48-$51 million in sustaining capital and $10-$12 million in growth capital”
Greens Creek Capital expenditures - Growth (… for FY2025
“$10 - $12”
Lucky Friday silver production for FY2025
“4.7-5.1 million ounces of silver”
Lucky Friday Silver Equivalent (Moz) for FY2025
“8.0 - 8.5”
Lucky Friday silver equivalent ounce for FY2025
“8.0-8.5 million silver equivalent ounces”
Estimated production impact at Keno Hill fro… for Q3 FY2025
“approximately 90,000 ounces of silver”
Casa Berardi gold production for FY2025
“76.0-82.0koz”
Casa Berardi total cost of sales for FY2025
“$180 million”
Casa Berardi Cash cost, after by-product cre… for FY2025
“$1,500-$1,650/oz”
Casa Berardi AISC, after by-product credits,… for FY2025
“$1,750-$1,950/oz”
Quarterly cash dividend on common stock for FY2025
“$0.00375 per share”
Quarterly cash dividend on Series B preferre… for FY2025
“$0.875 per share”
Consolidated silver production for FY2025
“15.5-17.0 million ounces”
Total Silver Production (Moz) for FY2025
“15.5 - 17.0”
Keno Hill silver production for FY2025
“2.7-3.1 million ounces”
Consolidated gold production for FY2025
“126-137 koz”
Greens Creek Silver Production (Moz) for FY2025
“8.1 - 8.8”
Greens Creek Gold Production (Koz) for FY2025
“50.0 - 55.0”
Greens Creek Gold Equivalent (Koz) for FY2025
“189.0 - 200.0”
Lucky Friday Silver Production (Moz) for FY2025
“4.7 - 5.1”
Lucky Friday Gold Production (Koz) for FY2025
“N/A”
Lucky Friday Gold Equivalent (Koz) for FY2025
“80.0 - 85.0”
Casa Berardi Silver Production (Moz) for FY2025
“N/A”
Casa Berardi Silver Equivalent (Moz) for FY2025
“6.5 - 7.5”
Keno Hill Silver Production (Moz) for FY2025
“2.7 - 3.1”
Keno Hill Gold Production (Koz) for FY2025
“N/A”
Keno Hill Silver Equivalent (Moz) for FY2025
“3.0 - 3.5”
Keno Hill Gold Equivalent (Koz) for FY2025
“30.0 - 40.0”
Total Gold Production (Koz) for FY2025
“126.0 - 137.0”
Total Silver Equivalent (Moz) for FY2025
“35.5 - 39.0”
Total Gold Equivalent (Koz) for FY2025
“375.0 - 407.0”
Total Silver Cash cost, after by-product cre… for FY2025
“($1.25)-($0.75)/oz”
Total silver AISC (after by-product credits,… for FY2025
“$11.50-$13.50/oz”
Lucky Friday total cost of sales for FY2025
“$165 million”
Greens Creek Total Costs of Sales (million) for FY2025
“289.0”
Greens Creek Cash cost, after by-product cre… for FY2025
“($7.00) - ($5.75)”
Greens Creek AISC, after by-product credits,… for FY2025
“($1.00) - $0.50”
Lucky Friday Total Costs of Sales (million) for FY2025
“165.0”
Lucky Friday Cash cost, after by-product cre… for FY2025
“$7.00-$7.50”
Lucky Friday AISC, after by-product credits,… for FY2025
“$20.00-$21.50”
Total Silver Total Costs of Sales (million) for FY2025
“454.0”
Total Silver AISC, after by-product credits,… for FY2025
“$11.00 - $13.00”
Casa Berardi Total Costs of Sales (million) for FY2025
“180.0”
Consolidated capital investment for FY2025
“$222-$242 million”
Exploration and pre-development expenditures for FY2025
“$28 million”
Total Capital expenditures - Total (millions) for FY2025
“$222 - $242”
Total Capital expenditures - Sustaining (mil… for FY2025
“$125 - $133”
Total Capital expenditures - Growth (millions) for FY2025
“$97 - $109”
Greens Creek Capital expenditures - Total (m… for FY2025
“$58 - $63”
Lucky Friday Capital expenditures - Total (m… for FY2025
“$63 - $68”
Lucky Friday Capital expenditures - Sustaini… for FY2025
“$58 - $61”
Lucky Friday Capital expenditures - Growth (… for FY2025
“$5 - $7”
Casa Berardi Capital expenditures - Sustaini… for FY2025
“$19 - $21”
Casa Berardi Capital expenditures - Growth (… for FY2025
“$39 - $42”
Keno Hill Capital expenditures - Growth (mil… for FY2025
“$43 - $48”
Exploration & Pre-Development for FY2025
“$28”
Exhibit 99.1 · the passage around this item
… earlier in the release
Free cash flow was $4.9 million and decreased over the prior quarter due to the items mentioned above.   Outlook There is no change to the 2025 production guidance for Lucky Friday, maintaining silver production guidance of 4.7-5.1 million ounces of silver, or 8.0-8.5 million silver equivalent ounces when factoring in all metals (silver, lead and zinc). Guidance for total cost of sales is maintained at $165 million (includes depreciation), with cash cost and AISC per silver ounce (after by-product credits) guidance also being maintained at $7.00-$7.50 and $20.00-$21.50 respectively. 3,4 Capital guidance for Lucky Friday in 2025 is unchanged, with investment expected to increase in the third quarter (relative to the second quarter) due to the seasonal construction period and ramping up construction activities. The third quarter is expected to be the lightest production quarter of the year due to the planned impact on hoist availability within the quarter as the ongoing surface cooling project (a key infrastructure project to increase the cooling capacity required for the mine over the reserve mine-life) requires use of this infrastructure to complete the project. The lower third quarter production outlook compared to the other 2025 quarters was captured in our original guidance for the full year released in February. Please refer to guidance section of the release for production, cost, and capital guidance for 2025.   Keno Hill - Yuk
later in the release …