Hecla Mining — Aug 4, 2025 release
Fiscal 2025 second-quarter results · 8-K Item 2.02 · Exhibit 99.1 · 0000950170-25-104148
Showing in the filing
Greens Creek silver production
“8.1-8.8 million ounces of silver”
Period
FY2025
Measure
Company-defined measure
Source
Prose
All guidance in this release · 65
Annual interest expense savings from Notes r… for FY2025
“$17.8 million annually”
Keno Hill Capital expenditures - Sustaining … for FY2025
“$0”
Greens Creek silver production for FY2025
“8.1-8.8 million ounces of silver”
Greens Creek gold production for FY2025
“50.0-55.0 thousand ounces”
Greens Creek Silver Equivalent (Moz) for FY2025
“18.0 - 19.5”
Greens Creek silver equivalent ounce for FY2025
“18.0-19.5 million silver equivalent ounces”
Greens Creek total cost of sales for FY2025
“$289 million”
Greens Creek AISC, after by-product credits,… for FY2025
“$0.00-$1.50”
Greens Creek Capital expenditures - Sustaini… for FY2025
“$48 - $51”
Greens Creek capital investment for FY2025
“$48-$51 million in sustaining capital and $10-$12 million in growth capital”
Greens Creek Capital expenditures - Growth (… for FY2025
“$10 - $12”
Lucky Friday silver production for FY2025
“4.7-5.1 million ounces of silver”
Lucky Friday Silver Equivalent (Moz) for FY2025
“8.0 - 8.5”
Lucky Friday silver equivalent ounce for FY2025
“8.0-8.5 million silver equivalent ounces”
Estimated production impact at Keno Hill fro… for Q3 FY2025
“approximately 90,000 ounces of silver”
Casa Berardi gold production for FY2025
“76.0-82.0koz”
Casa Berardi total cost of sales for FY2025
“$180 million”
Casa Berardi Cash cost, after by-product cre… for FY2025
“$1,500-$1,650/oz”
Casa Berardi AISC, after by-product credits,… for FY2025
“$1,750-$1,950/oz”
Quarterly cash dividend on common stock for FY2025
“$0.00375 per share”
Quarterly cash dividend on Series B preferre… for FY2025
“$0.875 per share”
Consolidated silver production for FY2025
“15.5-17.0 million ounces”
Total Silver Production (Moz) for FY2025
“15.5 - 17.0”
Keno Hill silver production for FY2025
“2.7-3.1 million ounces”
Consolidated gold production for FY2025
“126-137 koz”
Greens Creek Silver Production (Moz) for FY2025
“8.1 - 8.8”
Greens Creek Gold Production (Koz) for FY2025
“50.0 - 55.0”
Greens Creek Gold Equivalent (Koz) for FY2025
“189.0 - 200.0”
Lucky Friday Silver Production (Moz) for FY2025
“4.7 - 5.1”
Lucky Friday Gold Production (Koz) for FY2025
“N/A”
Lucky Friday Gold Equivalent (Koz) for FY2025
“80.0 - 85.0”
Casa Berardi Silver Production (Moz) for FY2025
“N/A”
Casa Berardi Silver Equivalent (Moz) for FY2025
“6.5 - 7.5”
Keno Hill Silver Production (Moz) for FY2025
“2.7 - 3.1”
Keno Hill Gold Production (Koz) for FY2025
“N/A”
Keno Hill Silver Equivalent (Moz) for FY2025
“3.0 - 3.5”
Keno Hill Gold Equivalent (Koz) for FY2025
“30.0 - 40.0”
Total Gold Production (Koz) for FY2025
“126.0 - 137.0”
Total Silver Equivalent (Moz) for FY2025
“35.5 - 39.0”
Total Gold Equivalent (Koz) for FY2025
“375.0 - 407.0”
Total Silver Cash cost, after by-product cre… for FY2025
“($1.25)-($0.75)/oz”
Total silver AISC (after by-product credits,… for FY2025
“$11.50-$13.50/oz”
Lucky Friday total cost of sales for FY2025
“$165 million”
Greens Creek Total Costs of Sales (million) for FY2025
“289.0”
Greens Creek Cash cost, after by-product cre… for FY2025
“($7.00) - ($5.75)”
Greens Creek AISC, after by-product credits,… for FY2025
“($1.00) - $0.50”
Lucky Friday Total Costs of Sales (million) for FY2025
“165.0”
Lucky Friday Cash cost, after by-product cre… for FY2025
“$7.00-$7.50”
Lucky Friday AISC, after by-product credits,… for FY2025
“$20.00-$21.50”
Total Silver Total Costs of Sales (million) for FY2025
“454.0”
Total Silver AISC, after by-product credits,… for FY2025
“$11.00 - $13.00”
Casa Berardi Total Costs of Sales (million) for FY2025
“180.0”
Consolidated capital investment for FY2025
“$222-$242 million”
Exploration and pre-development expenditures for FY2025
“$28 million”
Total Capital expenditures - Total (millions) for FY2025
“$222 - $242”
Total Capital expenditures - Sustaining (mil… for FY2025
“$125 - $133”
Total Capital expenditures - Growth (millions) for FY2025
“$97 - $109”
Greens Creek Capital expenditures - Total (m… for FY2025
“$58 - $63”
Lucky Friday Capital expenditures - Total (m… for FY2025
“$63 - $68”
Lucky Friday Capital expenditures - Sustaini… for FY2025
“$58 - $61”
Lucky Friday Capital expenditures - Growth (… for FY2025
“$5 - $7”
Casa Berardi Capital expenditures - Sustaini… for FY2025
“$19 - $21”
Casa Berardi Capital expenditures - Growth (… for FY2025
“$39 - $42”
Keno Hill Capital expenditures - Growth (mil… for FY2025
“$43 - $48”
Exploration & Pre-Development for FY2025
“$28”
Exhibit 99.1 · the passage around this item
… earlier in the release
Free cash flow was $69.0 million, an increase of 106% from the prior quarter as gross profit rose 30% from the prior quarter and from benefits from working capital changes and 22% lower capital investment. Outlook Revised Silver production guidance for 2025 at Greens Creek is unchanged at 8.1-8.8 million ounces of silver, gold production guidance is increased to 50.0-55.0 thousand ounces from 44.0-48.0 thousand ounces, or 18.0-19.5 million silver equivalent ounces, unchanged from prior silver equivalent ounce guidance when factoring in all metals (silver, gold, lead, zinc and copper) due to changes in our metal price assumptions. Greens Creek's cost outlook has been lowered, maintaining total cost of sales guidance at $289 million (includes depreciation) but lowering cash cost guidance to ($6.25)-($5.00) from the prior $0.25-$0.75 (after by-product credits), per silver ounce, and AISC to $0.00-$1.50 from $6.50-$7.25 (after by-product credits), per silver ounce. 3,4 Capital investment guidance is unchanged at $48-$51 million in sustaining capital and $10-$12 million in growth capital. Capital investment at Greens Creek is expected to increase in the third quarter due to the seasonal construction period, with no change to full year capital investment guidance. In early July, the mine shifted to partial self-generated power while Alaska Electric Light and Power, the utility company supplying power to Greens Creek, performs a planned 8-week maintenance shutdown, which will increase costs during this p
later in the release …
the item shown at left
other guidance in this release
Text is the filed exhibit, verbatim.